First Construction Act Case In The House Of Lords

 
FREE EXCERPT

Judgment was delivered yesterday in Melville Dundas v Wimpey - the first case concerning the Construction Act to reach the House of Lords. The case considers whether the JCT provisions which suspend a contractor's entitlement to payment in the event of insolvency fall foul of the Act. It also raises questions as to when a withholding may be made even though a valid withholding notice was not issued.

Background

Wimpey (as developer) entered into a contract with Melville Dundas (as contractor) for the construction of a housing development in Glasgow. The contract was a JCT Standard Form of Building Contract with Contractor's Design (1998 ed).

Melville Dundas made several applications for payment. One payment application was for around 400K. A valid withholding notice was not issued by Wimpey in relation to that application. Ordinarily, the lack of a valid withholding notice would leave Melville Dundas entitled to payment of the full amount.

However, shortly after making the application for payment, Melville Dundas became insolvent. Wimpey then terminated the contract on the basis of Melville Dundas' insolvency, and in reliance on clause 27.6 of the JCT 98 form refused to make any further payment.

Clause 27.6 of the JCT 98 form entitles a developer to terminate the contract in the event of contractor insolvency, and suspend payments pending a later final reckoning. (The corresponding provision of the JCT 05 form is clause 8.7). The purpose of clause 27.6 is to preserve the position of the developer in the event of the contractor becoming insolvent, so as to protect any right of abatement or cross-claim that the developer usually has due to the extra cost of arranging for others to complete the works (and other costs and losses).

It was contended by the contractor that clause 27.6 fell foul of the Construction Act because it purported to take away the contractor's right to payment in circumstances where a valid withholding notice was not issued and money was therefore due. Was the contractor right?

Decision

By the barest of margins (3-2), the House of Lords held that clause 27.6 of the JCT 98 form was valid, and that it entitled the developer to suspend making any further payment to the contractor, notwithstanding that the developer had failed to issue a valid withholding notice.

The majority judges recognised the importance of the payment provisions of the Construction Act in providing a contractor with cash flow during the life of the...